The trial run of train from Chattogram-Dohazari-Cox's Bazar-Gumdhum (CDCG) rail line is expected to begin in September next.
Project sources said the construction works of CDCG train route is going on in full swing. The CDCG authority is trying to complete the project before the extended schedule, reports BSS.
A total of 86 percent of the project work has already been completed. The construction works of 84 km railway lines of 128 km from Dohazari to Cox's Bazar has already been completed.
The constructions works of three railway stations out of nine has been completed. Constructions works more two or three railway stations will be completed by September next while the rest railway stations works is going on in full swing now.
Sources said that the schedule of the project was to be completed in June 2022 and it has been extended by two years until June 2024.
A total of 128 km single line and dual-gauge rail line is being constructed between Dohazari and Cox's Bazar.
Bd-pratidin English/Golam Rosul